Sunday, October 19, 2008

Florida Room renovations by Echo Atlantic Construction

We passed our framing and pre-lathe inspection Friday, and insulated and started drywall Saturday. The stucco contractor is scheduled to be there Monday morning, and could finish in one day, two at the most. Also my trim carpenter, whom I haven't worked with since Trade Wind Builders days, should swing by Monday to do a material take-off. If all goes well I could have the room hung, finished, and textured,and the window sills and trim done by Friday.

No comments: